Menai Bridge repairs delayed by another six months

Menai-Bridge.webp

Repair work to the Menai Suspension Bridge have actually been postponed by a minimum of another 6 months after engineers found water ingress on steelwork below the crossing.

The Welsh Government stated conclusion of stage 2 of the repair of the 200-year-old structure had actually been pressed back from spring to fall 2027.

The discovery implied the prepared protective paint system might not be used dependably.

Welsh deputy transportation minister Mark Hooper stated: “I was very dissatisfied and annoyed to gain from the specialists that their program of repair work, which has actually been besieged by many hold-ups, will be postponed when again.”

Wet covers on the steelwork emerged just after existing paint was eliminated from the underside of the bridge.

Upkeep operator UK Highways A55 resequenced the staying works while an alternative paint system efficient in enduring wetness and conference heritage requirements was determined.

The modified program will see traffic management procedures gotten rid of for the rest of 2026, although a 7.5-tonne weight constraint will stay throughout the phase-two works.

Hooper explained the most recent hold-up as “inappropriate”.

He stated he had actually composed to the president of facilities financier Equitix, which supervises UK Highways A55, and required an immediate conference over the modified program.

The most recent obstacle comes more than 4 years after Thomas Telford’s suspension bridge was closed following the discovery of major security threats related to its wall mounts in October 2022.

The very first stage of repair, including the replacement of all 168 wall mounts, was finished in October 2024.

The crossing was closed once again in October 2025 after examinations throughout phase-two works determined bolts on beams below the structure that required changing.

In January this year, then Welsh transportation secretary Ken Skates revealed an additional hold-up to the repair following extra engineering evaluations developing from the crossbeam concern.

Together with repainting, the 2nd stage consists of repair work to concrete corbels, recalibration of the land saddle and lighting upgrades.

The Welsh Government verified last month that advancement deal with a 3rd crossing of the Menai Strait would reboot, consisting of style work, ecological evaluations and company case advancement.

This story was sourced, established, inspected and modified by a human editor, with preparing and extra monitoring support from a bespoke Building and construction News AI tool.


Discover more from PMN S.P.O.R.T.S - A PRIME MEDIA NETWORK BRAND

Subscribe to get the latest posts sent to your email.

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Captcha verification failed!
CAPTCHA user score failed. Please contact us!

spot_imgspot_imgspot_imgspot_img