
Full-line testing preceding the opening of the long-delayed East Extension of Ottawa’s LRT Line 1 system will itself extend into at least the first full week of December.
Sign In or Create an Account
or
Article content
A memo on Thursday from OC Transpo general manager Rick Leary addressed to the mayor and city councillors said testing that began on Nov. 22 would continue through Nov. 27 before being suspended through Dec. 5 and resuming on Dec. 6 at the request of East-West Connectors, the consortium contracted to build the extension.
Article content
Article content
Article content
“EWC will complete preparatory work for upgrades to an element of the traction power system along the tracks,” Leary’s memo said. “The upgrades increase operational flexibility when managing service disruptions and shorten the time required to return to normal operations. This work has been prioritized to reduce impacts once the East Extension is in operation.”
Article content
By signing up you consent to receive the above newsletter from Postmedia Network Inc.
Article content
This past week featured the running of trains on Line 1 all the way from Tunney’s Pasture Station, currently its western-most point, to Trim Station in Orléans, although O-Train passengers had to disembark at what is now the eastern-most Blair Station.
Article content
For the first time, Leary’s memo said, Rideau Transit Maintenance was launching 23 trains running the extended line with trains operating approximately every four and a half minutes during peak periods to test vehicles, schedules, staffing assignments and the reliability of systems under normal operating conditions.
Article content
The testing revealed a number of items that East-West Connectors and Rideau Transit Maintenance needed to address, the memo said, including:
Article content
Article content
- EWC to make improvements to the power supply system between Blair and Trim stations;
- RTM to have trains consistently depart from the rail yard at the start of service;
- RTM to consistently make vehicles available for service;
- Hitachi to make improvements to the train-control system performance in the East Extension;
- EWC to repair a switch near Blair Station;
- Hitachi to address software issues affecting vehicles docking at Trim Station.
Article content
Article content
Leary’s memo said identifying these issues was a “normal part of the testing process” and a fundamental objective of this phase of testing, allowing for corrections and improvements in advance of the Pre-Trial Running and Trial Running that must be completed before full service on the East Extension could begin.
Article content
Article content
Take control of your search results. Make the Ottawa Citizen a preferred source on Google and see verified local reporting first.
Article content
Discover more from PMN S.P.O.R.T.S - A PRIME MEDIA NETWORK BRAND
Subscribe to get the latest posts sent to your email.





