Contractor, govt depts blamed over QMH faulty lifts

The Development Bureau has actually recognized shortages and drawbacks by the specialist, specialists and federal government departments in the setup of defective lifts at Queen Mary Hospital’s brand-new medical block.

President John Lee purchased an examination in September after the majority of the lifts in the 34-storey tower were sealed.

In a report sent to the Legislative Council on Thursday, the Development Bureau stated all 28 lifts in the structure experienced issues to differing degrees.

It stated “verticality deviations” in the lift shaft walls and guide rails throughout various floorings suggested the lift cars and trucks might not take a trip efficiently. The centre of gravity for the lift cars and trucks was likewise imbalanced, and the general craftsmanship quality was bad.

“A lift operating normally will experience a certain degree of minor displacement depending on the load conditions. However, if the clearance between the shaft wall and the lift car is insufficient, it can easily trigger the lift’s safety devices, thereby causing the lift to stop operation,” the report read.

Since Tuesday, correction work had actually been finished on 18 lifts, 7 of which were currently in operation after passing examinations.

Repair work for the staying lifts were anticipated to end up within this year.

The bureau included that ATAL Engineering Group, as the specialist, “bears overall responsibility” in guaranteeing the job is finished in accordance with requirements.

The report declared that the company understood measurement and verticality issues in the shaft, however “followed up sloppily” The issues might not be resolved in a prompt way.

The Development Bureau will take disciplinary action versus the specialist, in addition to the subcontractor and consultancy companies.

This might consist of the suspension of tendering rights, downgrading or delisting.

“As the investigation discovered that the incident may involve other illegal activities, we have referred the matter to the relevant law enforcement authorities for further investigation,” the report stated.

It likewise stated the Architectural Services Department stopped working to strictly comply with internal standards when releasing the certificate of conclusion in January 2025.

“We have requested the director of architectural services to deal with the involved personnel appropriately in accordance with the Civil Service Regulations. The director of architectural services is currently liaising with the Civil Service Bureau to discuss the arrangements for initiating disciplinary proceedings,” according to the file.

The Electrical and Mechanical Services Department was discovered to have actually abided by treatments in processing the applications for the lifts’ operation allows, however “some personnel” did not perform extensive examinations, and the department was prompted to provide advisory letters to them, explaining locations for enhancement.

Authorities will inform legislators at a Legco advancement panel conference on Friday.

Modified by Edmond Fong


Discover more from PMN S.P.O.R.T.S - A PRIME MEDIA NETWORK BRAND

Subscribe to get the latest posts sent to your email.

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Captcha verification failed!
CAPTCHA user score failed. Please contact us!

spot_imgspot_imgspot_imgspot_img